Company ABC is considering an investment in a new project. The company has an option of two projects A & B. The project A will require an initial outlay of Rs.100,000 and project B will require Rs.120,000. The discount rate for both projects is 12% and both projects are expected to generate following cash flows at the end of years:
Year Project A Project B
Rs. Rs.
1 50,000 60,000
2 40,000 40,000
3 50,000 50,000
Calculate net present value of both projects and suggest which project is more feasible. Show complete calculation with formulas.
Year Project A Project B
Rs. Rs.
1 50,000 60,000
2 40,000 40,000
3 50,000 50,000
Calculate net present value of both projects and suggest which project is more feasible. Show complete calculation with formulas.
Idea Solution:-
PROJECT (A)
PROJECT A INITIAL INVESTMENT IS 100000
R = 12%
R =12/100 =.12
FORMULAS
PV =FV/ (1+R)^T
NPV =EXPECTED CASH FLOW - COST
NOW FIRST WE FIND PV
FORMULA FOR PV IN T PERIOD IS
PV =FV/(1+R)^T
PV =50000/(1+.12)+40000/(1+.12)^2 + 50000/(1+.12)^3
PV =50000/1.12 +40000/1.12)^2 + 50000/(1.12)^3
PV =50000/1.12 + 40000/1.25 + 50000/1.40
PV =44642.8571 +31887.7551 +35589.0124
PV =112119.6246 EXPECTED CASH FLOW
NOW NPV IS
NPV = EXPECTED CASH FLOW- COST
NPV =112119.6246 – 100000
NPV =12119.6246
PROJECT (B)
PROJECT B INITIAL INVESTMENT IS 120000
R = 12%
R =12/100 =.12
FORMULA
PV =FV/(1+R)^T
NOW FIRST WE FIND PV
FORMULA FOR PV IN T PERIOD IS
PV =FV/ (1+R)^T
PV =60000/(1+.12) + 40000/(1+.12)^2 + 50000/(1+.12)^3
PV =60000/1.12 + 40000/1.25 + 50000/1.40
PV =53571.4286 + 31887.7551 +35589.0124
PV =121048.1961 EXPECTED CASH FLOW
NOW NPV IS
NPV = EXPECTED CASH FLOW- COST
NPV =121048.1961 – 120000
NPV =1048.1961
PROJECT A IS MORE FEASIBLE THAN THE PROJECT B
PROJECT A INITIAL INVESTMENT IS 100000
R = 12%
R =12/100 =.12
FORMULAS
PV =FV/ (1+R)^T
NPV =EXPECTED CASH FLOW - COST
NOW FIRST WE FIND PV
FORMULA FOR PV IN T PERIOD IS
PV =FV/(1+R)^T
PV =50000/(1+.12)+40000/(1+.12)^2 + 50000/(1+.12)^3
PV =50000/1.12 +40000/1.12)^2 + 50000/(1.12)^3
PV =50000/1.12 + 40000/1.25 + 50000/1.40
PV =44642.8571 +31887.7551 +35589.0124
PV =112119.6246 EXPECTED CASH FLOW
NOW NPV IS
NPV = EXPECTED CASH FLOW- COST
NPV =112119.6246 – 100000
NPV =12119.6246
PROJECT (B)
PROJECT B INITIAL INVESTMENT IS 120000
R = 12%
R =12/100 =.12
FORMULA
PV =FV/(1+R)^T
NOW FIRST WE FIND PV
FORMULA FOR PV IN T PERIOD IS
PV =FV/ (1+R)^T
PV =60000/(1+.12) + 40000/(1+.12)^2 + 50000/(1+.12)^3
PV =60000/1.12 + 40000/1.25 + 50000/1.40
PV =53571.4286 + 31887.7551 +35589.0124
PV =121048.1961 EXPECTED CASH FLOW
NOW NPV IS
NPV = EXPECTED CASH FLOW- COST
NPV =121048.1961 – 120000
NPV =1048.1961
PROJECT A IS MORE FEASIBLE THAN THE PROJECT B
Please do make changes in these assignment otherwise every one who copy this assignment as it is will awarded zero marks
NOTE: - These Assignments OR Quiz are just for idea, so kindly don't copy it, after viewing it make your own. Thanks We always try our best to upload 100% correct solution BUT it is requested that you kindly review it before submission, please BEST OF LUCK, Thanks to those students those send me Assignments and quizzes. If you have any Assignment and quiz kindly send at fascobuk@gmail.com
No comments:
Post a Comment